Stead Street pump station replacement
May 2020 | Government announces $25 million funding for “shovel ready” climate resilience projects. Environment Southland receives a funding contribution towards replacement axial flow pumps and a new modest pump house at an estimated cost of $3.5 million. |
September 2020 | The National Policy Statement for Freshwater 2020 comes into force with a requirement for the provision of safe fish passage. |
October 2020 | Southlanders are invited to submit on a proposed co-funding arrangement where the Government funds 75% or $13.875m of their climate resilience projects and Environment Southland funds 25% or $4.625m. Because the Government’s funding was unexpected, the Council plans to use existing reserves of up to $1.5 million for these projects in the 2020-21 year and consult on funding the remainder of its contribution, up to $3.125 million, as part of the 2021-2031 Long-term Plan—total ES contribution $4.625 million. |
April - May 2021 | Council consults on a 25% contribution of $4.8m to the climate resilience projects (versus the initial $4.625m) with a plan to borrow the money to complete these projects over the next two years. |
July 2021 | Environment Southland announces the order of two Archimedes screw pumps designed to provide safe fish passage. The design of the new pump station needs to accommodate these large new-generation pumps. Long Term Plan adopted. Chairman Nicol Horrell notes that “the major increase in work stems from community expectations and central government requirements in relation to freshwater and climate change”. Also, for the Climate Resilience Projects Local Share Funding (Shovel Ready Projects), the plan states, “For the duration of the LTP we have budgeted to initially fund the climate resilience projects from debt. Investment in climate resilience projects in the 2021 financial year of $388,000 was funded from appropriate reserves. As the circumstances of each catchment in the project are different, final funding options will be considered after the completion of each project.” |
August 2021 | Council agrees to contribute $5.125 million to the climate resilience projects in a co-funding arrangement with Kānoa following 2020-21 community consultation. |
September 2021 | Concept plans for news pump station shared with Council. |
December 2021 | Kānoa representatives Regional Economic and Development Unit investment director Eliot Linforth-Hall and climate resilience project advisory board chair Basil Chamberlain visit the Stead Street pump station site and meet with project staff while also inspecting progress with the ICC Stead Street climate resilience project. |
January 2022 | Presentation to Council about designs for the new Pump Station and projected budget increase. |
June 2022 | Annual Plan approved. Council highlights the following change from the Long Term Plan in the previous year: “a review of the climate resilience projects, which has been built into the budget to provide to provide for potential increased costs given cost increases being seen in the national construction sector.” |
September 2022 | Contract for Stead St Pump Station replacement signed with Fulton Hogan. The contract price for the pump station is $8.3 million, bringing the projected total construction cost, including design and provision of twin Archimedes screw pumps, to $11 million. This is an increase of $4.5 million above the projected cost of $6.5 million in the 2021/22 Annual Plan. |
October 2022 | Construction underway. |
August 2023 | An update given on the Stead Street Pump Station climate resilience project to the Finance and Performance Committee, and a press release issued regarding the floor height and height of pump supports within the pump station. |
September 2023 | Environment Southland and its design consultant and contractor agree to a solution regarding the design and construction issues with the Stead Street Pump Station. Environment Southland seeks advice on recovering the cost of the remedial solution from the parties involved and is not expecting an increase in the project budget. |
March 2024 | Remedial works completed and construction of the pump house underway. |
April 2024 | Twin Archimedes screw pumps installed. |
April 2024 | Council is advised that the new facility's indicative commissioning date will be mid-to-late June 2024. The remedial works took longer than anticipated, primarily due to the significant hydro demolition required to prevent damage to the existing reinforcing and maintain the building's structural integrity. |
May 2024 | Indicative commissioning date re-scheduled for mid-to-late July 2024 due to wet weather delaying electrical installation, which requires a watertight building envelope. |
July 2024 | Contract completion date for the new pump station is confirmed for late July 2024. |